Morgan Stanley believes that the U.S. election is substantially disrupting the pace of AI data center construction—approximately 5 GW of capacity will be delayed from 2028 to 2029, and up to 40% of chip deployments between 2026 and 2028 face risks of delayed power connectivity. The combined pressures of power shortages, political resistance, and rising costs are accelerating capital shifts toward overseas markets such as Southeast Asia and India, potentially extending the overall AI capital expenditure cycle.Author and source: Xu Chao
Morgan Stanley’s latest research shows that political resistance triggered by the U.S. midterm elections is substantially altering the pace of AI data center construction, with approximately 20% of the new capacity originally scheduled to come online in 2028 being delayed until 2029. Around 40% of the chips deployed in the U.S. between 2026 and 2028 face the risk of not being powered on in time. This assessment will have cascading effects on the technology supply chain, the data center financing market, and the overall capital expenditure cycle for AI.
According to Morgan Stanley’s report dated November 9, the firm expects approximately 5 GW of U.S. data center projects to be delayed from 2028 to 2029. After adjustment, annual U.S. data center capacity additions in 2028 are projected to decline by 4% year-over-year (while global capacity grows by 9% during the same period), followed by a 38% rebound in 2029 (with global growth at 20%). Between 2026 and 2028, the 116 GW of power demand corresponding to U.S. chip shipments faces a net potential grid connection gap of 44 GW, accounting for approximately 38% to 40% of total demand, primarily due to insufficient grid capacity, ongoing projects yet to be completed, and power supply delays related to the midterm elections.

The report clearly states that the policy tools capable of effectively constraining project progress are primarily held by state and local governments, and the federal political landscape has limited direct impact on specific projects.
Morgan Stanley believes that the newly elected governors are unlikely to interfere with projects already under construction, so the 2027 project timeline remains unchanged; however, some projects originally scheduled for 2028 in Texas and Ohio may be delayed due to new requirements being negotiated between the governors and state legislatures. The four primary impacts are: a more dispersed selection of data center locations (including a shift overseas), increased premiums on existing capacity, a potential阶段性空档 risk in the 2028 technology supply chain, and an overall elongation of the AI capital expenditure cycle.
Political resistance alters the pace of development, with 2028 serving as a turning point.
Morgan Stanley's report highlights that opposition to AI and data center expansion was a clear point of voter division in this midterm election. A survey conducted by the firm in August 2026 found that 72% of likely voters considered candidates' positions on AI "very important" or "somewhat important," with this figure rising to 76% among those aged 18 to 34.

However, the report emphasizes that the conversion of campaign pledges into actual policy restrictions remains constrained by procedural factors. Although the Democratic Party achieved significant victories in gubernatorial races in key states such as Texas and Ohio, control of state legislatures remains divided between the two parties, making it difficult for governors to implement their unilateral proposals without going through the legislative process.
Disruptions to ongoing projects are expected to be limited. The report concludes that the new governor is more likely to exert influence by collaborating with the legislature and establishing new approval requirements for data center developers, rather than directly halting construction. This logic leads the report to maintain its 2027 construction outlook, with adjustments focused on new project starts in 2028.
The power shortfall is a more fundamental constraint.
Beyond political considerations, the report identifies insufficient power supply as the core constraint limiting chip deployment from 2026 to 2028.
According to Morgan Stanley's waterfall model, the total electricity demand corresponding to U.S. chip shipments from 2026 to 2028 is 116 GW; after deducting the 25 GW covered by under-construction data centers and the 21 GW available grid capacity, and adding the additional 6 GW shortfall due to election-related power supply delays, the potential power deficit reaches 76 GW.

On this basis, alternative power solutions such as turbines, Bloom Energy fuel cells, and nuclear power can alleviate 27 GW; shifting deployment to Asia can further reduce the gap by an additional 5 GW, ultimately narrowing the net potential shortfall to 44 GW, or approximately 40% of the total demand of 116 GW.
The United States remains the largest market, but demand from overseas is rising.
Morgan Stanley estimates that the U.S. market leadership will not be fundamentally altered by the outcome of this midterm election. Based on 2025 as the baseline, the U.S. is expected to add approximately 103 GW by 2030, China around 55 GW, and Europe about 13 GW.
However, the midterm election results could further encourage U.S. developers to look overseas. Morgan Stanley identifies Southeast Asia (+6 GW), India (+7 GW), Europe (+12 GW), Australia (+4 GW or more), Japan (+2 GW), and South Korea (+2 GW) as viable regions capable of reasonably absorbing U.S. data center capacity. The report also notes that the additional capacity in Europe is expected to primarily serve local European demand.

When selecting overseas locations for construction, construction costs and electricity prices are the two most critical considerations. The report estimates that data center construction costs are rising at an annual rate exceeding 10%, driven by factors such as the energy crisis, rising interest rates, demand for grid investment, and increasing labor costs. GPUs account for approximately half of the total capital expenditure per GW of AI data centers, making them the single largest component in capital allocation.
Capital expenditure forecasts for hyperscale tech companies remain unchanged, with credit markets showing signs of quality divergence.
Morgan Stanley maintains its capital expenditure forecasts for mega-tech companies such as Google's parent company GOOGL, Amazon, Microsoft, and Meta.
According to its estimates, the combined capital expenditures of the aforementioned institutions are projected to rise from approximately $481 billion in 2025 to about $951 billion in 2026, $1.64 trillion in 2027, and further increase to approximately $1.76 trillion in 2028. The growth rate is expected to slow significantly, from 98% in 2026 and 73% in 2027 to just 7% in 2028. The report also notes that if construction delays materialize in 2028, there is a possibility of downward revision to that year’s capital expenditures.

At the credit market level, the report observes a clear quality divergence within AI financing. Bond issuance by high-quality, ultra-large technology companies has recently rebounded, but their credit spreads have widened to the widest levels of the year, exceeding those of broad investment-grade bond indices, despite generally higher credit ratings. Meanwhile, debt issuance for data center construction, which is more sensitive to interest rates, has significantly slowed, and related bonds have underperformed same-rating indices since the summer.

Morgan Stanley expects an increase in chip financing deals and bond issuances by large tech companies with shorter maturities. As the market reassesses the risk premium for data center construction, data center bonds are expected to remain highly volatile. If the pace of construction slows, the pressure from new financing supply may be somewhat alleviated.